Explanation of Red Oak Wastewater Treatment Situation from Superintendent, Clint Roland
Red Oak’s Water and Wastewater Superintendent, Clint Roland was in the KCSI studio Tuesday to talk about the plant those sewer rates are meant to pay for. The spring storm showed the vulnerabilities the crew already knew about. At one point the plant was about 80 percent down. Parts took months. Most of it is running again. It is not fixed.
The new plant is being designed for a peak of about 4 million gallons a day. Red Oak is running about 1 million gallons a day now, and the plant is at roughly 75 to 80 percent of capacity. Kotter put the utility customer count near 3,000. Roland said the design includes about 20 percent growth and a small industrial base, which is what the Iowa DNR and the EPA require from a 10-year flow record. He also said the cost of building for 1 million gallons versus 4 million is close, because the expensive pieces are the same. The difference is mostly concrete in the tanks.
The loan is a revenue bond, paid by the ratepayers, not a general-obligation bond backed by property taxes. Kotter said there is no statutory cap on a revenue bond the way there is on tax-backed debt. She said the city will still land in the range of neighboring towns, and that anyone who is struggling should call and set up a payment plan. Disconnections do not happen when a customer is talking to the city and paying something.
Roland’s offer: call him. He will set a time for a tour or a sit-down. “If someone really wants to know what’s going on, give me a call.”

Leave a Reply
Your email is safe with us.